Roofing installation commences

Project:

M1 Business Park

Update:

29th March 2024

Milestone:

Roofing Installation

We are pleased to provide you with another comprehensive update on the progress of our construction project. As we continue to monitor developments on site, we are delighted to report that our construction progress is currently ahead of schedule. This accomplishment is largely attributed to favourable weather conditions and the efficient coordination of trades by our builder, ensuring optimal utilisation of resources and adherence to the construction program.

A significant milestone has been reached with the commencement of installation activities for roofing sheets and insulation, as well as the installation of roofing mesh netting, across warehouses 24, 25, 26, 27, 28, 29, 30, 31, 32 and 33. This phase marks a critical step forward in the construction of stage 1 units, signifying the transition to the next phase of development. Once the roofing installation is finalised, these units will be shielded from adverse weather conditions, providing our builder with a conducive environment to initiate internal fit-out works in a clean, safe, and uninterrupted manner.

It is important to note that the installation of roofing works is a process that will require several days to complete, ensuring precision and adherence to quality standards. Throughout this period, we will continue to monitor progress closely, ensuring that every aspect of the construction process aligns with our project's overarching objectives.

As we progress through this exciting journey, we remain steadfast in our commitment to transparency and communication. We recognise the importance of keeping you informed at every stage of development, and we will continue to provide regular updates as we navigate the various milestones ahead.

 

UPCOMING CONSTRUCTION WORKS:

Installation of precast panels to warehouses 22 and 23

Installation of precast panels to warehouses 1, 4, 5, 6, 7, 8 and 9

Installation of services to central warehouses

Thank you for your continued support and confidence in our project. Should you have any questions or require further information, please do not hesitate to reach out to us.

Previous
Previous

March ONSITE CONSTRUCTION VIDEO

Next
Next

Stage 2 slabS COMPLETE